Guwahati, November 17: An army official on Friday said that some areas of northern Sikkim which were cut off from the mainland after the flash flood hit the hill state in the first week of October, have now been connected again. Lt. Col. Mahendra Rawat, PRO Guwahati, said, “Troops of the Trishakti Corps of the Indian Army, with the assistance of the Border Road Organisation (BRO), completed the bailey bridge over the Teesta River at Chungthang. Indian Army Ramps Up AI, but How Effective Will It Be?.
This has finally connected the flood-affected areas of North Sikkim with the mainland that has been cut off since the night of October 3.” “The bridge will now pave the way for seamless movement of vehicles and the provision of relief material to these flood-affected areas,” he added.
Bailey Bridge in Sikkim Restored:
#WATCH | Troops of Trishakti Corps Indian Army with assistance from BRO completed the Bailey bridge over Teesta River at Chungthang, Sikkim. This has finally connected the flood-affected areas of North Sikkim with the mainland that was cut off since the night of 3rd October. The… pic.twitter.com/J9UKYQ5xDN
— ANI (@ANI) November 16, 2023
Indian Army, BRO Build Bailey Bridge:
The #IndianArmy, in collaboration with the Border Roads Organization (BRO), has successfully completed the construction of the #Baileybridge over the Teesta River at Chungthang. pic.twitter.com/8VW23bJg8V
— News Daily 24 (@nd24_news) November 16, 2023
According to an official statement of the Indian Army, “The 200-feet Bailey Bridge is an engineering marvel in itself, as it is the longest and heaviest single-span bailey bridge that can be launched." Sikkim Shocker: 15-Year-Old Boy Kidnapped in Gangtok Rescued From Bihar’s Madhepura, Three Accused Arrested.
Traffic Resumes:
VIDEO | Traffic through Chungthang Bailey Bridge over the Teesta River in North #Sikkim resumes. The Indian Army's Trishakti Corps in collaboration with the Border Roads Organisation (BRO) successfully completed the construction of the bridge which was washed away during flash… pic.twitter.com/9QjPWNXjv8
— Press Trust of India (@PTI_News) November 16, 2023
“Working round the clock, the BRO initially constructed the concrete abutments, followed by the bridge construction by Trishakti Sappers, which took around five days,” the statement further mentioned. The Army officer mentioned that engineer troops of the Trishakti Corps and BRO, along with several heavy earthmoving plants, were employed for this bridging operation.
(The above story first appeared on LatestLY on Nov 17, 2023 02:05 PM IST. For more news and updates on politics, world, sports, entertainment and lifestyle, log on to our website latestly.com).