New Delhi, Nov 21 (PTI) The Delhi Metro Rail Corporation is constructing three double-decker viaducts, which will integrate both metro rail and road traffic, as part of its ambitious Phase 4 expansion, a senior official said.

The viaducts are being build on the corridors of Majlis Park-Maujpur, Aerocity-Tughlakabad , and Janakpuri West-RK Ashram Marg, the official said.

Also Read | Sikkim State Lottery Result Today 6 PM Live, Dear Dancer Thursday Lottery Sambad Result of 21.11.2024, Watch Live Lucky Draw Winners List.

"The Delhi Metro is building three rail-cum-road flyovers as part of the Phase 4 expansion work. On the Majlis Park-Maujpur corridor, an integrated elevated viaduct i.e. a double-decker structure with PWD flyover at the lower deck and metro line at the upper deck is being constructed between Bhajanpura and Yamuna Vihar stations," DMRC principal executive director Anuj Dayal said.

In this structure, the construction of the double-decker portion except the ramps has been completed. The ramp for the road portion shall be completed only after getting the mandatory tree-cutting permissions, he said.

Also Read | Latest Government Jobs Notifications: National Institute of Ayurveda Invites Applications for 31 Vaidya, Pharmacists and Other Posts, Apply Online at nia.nic.in.

The construction of another double-decker viaduct at the Ambedkar Nagar T Point on the Aerocity-Tughlakabad corridor of the Phase-4 is currently under progress.

Launching work of the pier caps at the metro level has been started and installation of crossbeams for the road flyover level has also been initiated. This shall be south Delhi's first such construction where a metro line and a road flyover are being constructed one below the other - the road flyover at level 1 and the metro track at level 2, he said.

On the Janakpuri West–RK Ashram Marg corridor as well, a 630-metre-long double-decker section will come up between Azadpur and Ashok Vihar. On this section, foundation work has been almost completed and pier work is nearing completion, Dayal added.

Earlier, the DMRC said that a target of 2026 has been set for operationalising the new 65-kilometre network.

Though work on the fourth phase expansion project started in December 2019, progress was significantly impacted from 2020 to 2022 due to the Covid pandemic and delays in getting permissions to cut trees.

The DMRC is undertaking construction work on 65.2 km spanning 45 stations under the project's three priority corridors: Janakpuri West-RK Ashram Marg (28.92 km), Majlis Park-Maujpur (12.55 km), which are extensions of the already operational Magenta Line and Pink Line; and the Aerocity-Tughlakabad (23.62 km) Corridor, connecting the operational Violet Line and Airport Line from the respective ends.