New Delhi, Mar 27 (PTI) State-owned engineering firm Bharat Heavy Electricals Ltd (BHEL) has received an order worth Rs 4,000 crore from Adani Power Limited for setting up the 1,600 MW Raigarh Phase-II Thermal Power Plant at Raigarh, Chhattisgarh.

BHEL in a filing said that it received a Letter of Award on March 27, 2024, for the supply of equipment and supervision of erection & commissioning for 2x800 MW power project based on supercritical technology at Raigarh Phase II, Chhattisgarh.

Also Read | Francis Scott Key Bridge Collapse in Baltimore: Things to Know About Key Bridge aka Beltway Bridge in the US That Collapsed Into River After Being Struck by Cargo Ship.

The boiler and Turbine Generator are to be manufactured at BHEL's Trichy and Haridwar plants respectively.

The supply of Unit-1 will take 31 months and Unit-2 (35 months).