Mumbai Metro 3 Between SEEPZ and Bandra Kurla Complex To Be Completed by End of December 2024
In the Cabinet meeting presided over by Maharashtra's Chief Minister Eknath Shinde on Wednesday, gave its nod to give state government's share of Rs 1,163 crore directly to the Mumbai Metro Rail Corporation, instead of the Mumbai Metropolitan Region Development Authority (MMRDA).
Mumbai, June 27: In the first cabinet meeting held on Wednesday, the Maharashtra Government decided to complete the Mumbai Metro 3 project by the end of December 2024. The first phase of Mumbai Metro 3, will run between SEEPZ (Santacruz Electronics Export Processing Zone) and Bandra Kurla Complex. The project will be completed by the end of December 2024 which was initially scheduled to be completed by September 2024.
In the Cabinet meeting presided over by Maharashtra's Chief Minister Eknath Shinde on Wednesday, gave its nod to give state government's share of Rs 1,163 crore directly to the Mumbai Metro Rail Corporation, instead of the Mumbai Metropolitan Region Development Authority (MMRDA). Mumbai Metro 3 Update: MMRCL Commences Integrated Trial Runs for Metro 3 Between BKC and Aarey (Watch Video).
According to the government, the project has achieved the completion of 98 percent and its revised cost is Rs 37,275.50 crore. Line 3 (Aqua Line) of the Mumbai Metro is a rapid transit metro line in the city of Mumbai, Maharashtra, India.
(This is an unedited and auto-generated story from Syndicated News feed, LatestLY Staff may not have modified or edited the content body)