India News | Construction Work at Nyoma Mudh Advanced Landing Ground (ALG) Underway Despite Varying Climatic Conditions, Expected to Finish by August 2025

Get latest articles and stories on India at LatestLY. The construction work at Nyoma Mudh Advanced Landing Ground (ALG) is underway in spite of varying climatic conditions in Ladhak's Leh district.

Visuals from the construction site in Leh (Photo/ANI)

Leh (Laddakh) [India], November 13 (ANI): The construction work at Nyoma Mudh Advanced Landing Ground (ALG) in Ladakh is underway in spite of varying climatic conditions in the district.

The administrative approval for the construction of basic facilities in Mudh-Nyoma ALG was issued on March 20, 2023.

Also Read | Rajasthan Assembly By-Elections 2024: 24.83% Turnout Recorded Till 11 AM As Voting Continues for 7 Constituencies.

The contract was awarded to KCC Global Pvt. Ltd. on August 20, 2023, for an amount of 218 Cr on EPC Mode. The runway for ALG has already been completed within 14 months of the awarding contract.

The project is expected to be completed by August 2025. Around 800 labourers were employed during peak working season, a mix of both locals and skilled persons outside of Ladakh.

Also Read | Hezbollah Attacks Israel: Teachers' Quick Thinking Saves Lives of Kindergartners From Drone Attack.

The runway is bi-directional, which means aircraft can land and take off from both directions.

Notably, aircraft like C-130, AN-32, MI-17, and ALH can land on this airfield.

Site engineer Shaheed Saifi said that he felt proud to be part of this project, which is established near the border of China.

"To work here is challenging as the climatic conditions here vary from those in the plain areas; I have been here for the last five to six months," he said.

Describing challenges, he said that the major challenge was resources, as we had to bring our resources from the plains.

"There are a total of 70 labourers working here with two supervisors. The landing ground is multipurpose. Fighter jets and cargo can land here," he stated.

Brigadier Vishal Srivastava said "As far as the runway is concerned, it is almost complete, we will have a joint inspection with the Air Force. This airfield is above 13,00 feet, it is a forward area near LAC. Our troops are deployed in forward areas, this will help our troops in deployment, logistics, induction and medical evacuation. This will also bring socio economic development in the region." (ANI)

(This is an unedited and auto-generated story from Syndicated News feed, LatestLY Staff may not have modified or edited the content body)

Share Now

Share Now